Bidder Selection Plan

To renovate and upgrade Le Quang Hoa Street (UD.32) section from DT.387 to Nguyen Van Linh Street (National Highway 5);

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 14:38 15/05/2023
Contractor Selection Plan ID
PL2200018224-01
Publishing time
14:29 15/05/2023
Posting Status
Published
Contractor selection plan name
To renovate and upgrade Le Quang Hoa Street (UD.32) section from DT.387 to Nguyen Van Linh Street (National Highway 5);
Investment objective
Invest in building roads to connect central areas and industrial parks, ensuring the circulation of goods and travel of people and businesses located in the town. Gradually improve the infrastructure to create momentum for the town's socio-economic development and ensure synchronous investment in technical infrastructure and landscape architecture in urban areas, creating a good living environment for the people and community profit; consistent with policies to encourage and support urban development investment projects.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2200014887-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
4 Years
Location
Authority that issues the decision
Ủy ban nhân dân thị xã Mỹ Hào
Approval date
09/05/2023
Approval ID
1292/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Tender package No 08: Valuation consultancy
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
2.Package 09: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên
3.Package 02: Project Management
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
4.Package 03: Topographic survey consultancy, surveying tasks, construction drawing design and construction cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
5.Package 04: Consultancy and verification of construction drawing design and construction cost estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
6.Package 06: Consulting for appraisal of bidding documents, technical management of construction packages: construction and traffic safety assurance for construction; construction supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên
7.Package 01: Construction and traffic safety assurance for construction
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên
8.Package 10: Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên
9.Bidding package No. 05: Consulting on setting up bidding documents, evaluating bids for bidding packages: construction and ensuring traffic safety for construction; construction supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên
10.Package 07: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Town budget and other legal sources of capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Mỹ Hào District, Hưng Yên

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "To renovate and upgrade Le Quang Hoa Street (UD.32) section from DT.387 to Nguyen Van Linh Street (National Highway 5);". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "To renovate and upgrade Le Quang Hoa Street (UD.32) section from DT.387 to Nguyen Van Linh Street (National Highway 5);" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second