Bidder Selection Plan

Supplementing the contractor selection plan for the construction investment project of My Thuan 2 bridge and the two bridge paths under the project to build a number of expressways on the East North-South route in the period 2017-2020

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 08:41 12/06/2023
Contractor Selection Plan ID
PL2300026779-01
Publishing time
08:37 12/06/2023
Posting Status
Published
Contractor selection plan name
Supplementing the contractor selection plan for the construction investment project of My Thuan 2 bridge and the two bridge paths under the project to build a number of expressways on the East North-South route in the period 2017-2020
Name of project
Component project of investment and construction of My Thuan 2 bridge and the two paths leading to the two ends of the bridge under the project to build a number of expressway sections on the East North - South route in the period 2017-2020
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Nationally Important Project
Project implementation time
4 Years
Location
Authority that issues the decision
Bộ Giao thông vận tải
Approval date
24/05/2023
Approval ID
633/QĐ-BGTVT ngày 24/5/2023
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 2
1.Tender package TV.08: Completed project settlement audit consulting
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
2.Tender package TV.09: Consulting on traffic safety inspection before putting the works into operation
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Supplementing the contractor selection plan for the construction investment project of My Thuan 2 bridge and the two bridge paths under the project to build a number of expressways on the East North-South route in the period 2017-2020". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Supplementing the contractor selection plan for the construction investment project of My Thuan 2 bridge and the two bridge paths under the project to build a number of expressways on the East North-South route in the period 2017-2020" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second