Bidder Selection Plan

Project contractor selection plan Investment and renovation of 87B relay system at 110kV substations in 2022

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 15:07 16/06/2023
Contractor Selection Plan ID
PL2200085265-02
Publishing time
14:58 16/06/2023
Posting Status
Published
Contractor selection plan name
Project contractor selection plan Investment and renovation of 87B relay system at 110kV substations in 2022
Name of project
Investment project to renovate relay system 87B at 110kV substations in 2022
Investment objective
Renovating relay system 87B at 110kV substations in 2022
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
Tổng công ty Điện lực miền Nam
Approval date
26/12/2022
Approval ID
2647/QĐ-EVNSPC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Shopping VTTB
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Commercial loans and counterpart funds for construction investment in 2022 EVNSPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
Bình Minh Town, Vĩnh Long
2.Supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Commercial loans and counterpart funds for construction investment in 2022 EVNSPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
Bình Minh Town, Vĩnh Long
3.Construction, testing and calibration of station equipment and Scada . system
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and counterpart funds for construction investment in 2022 EVNSPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
Bình Minh Town, Vĩnh Long
4.Audit of completed project settlement reports
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and counterpart funds for construction investment in 2022 EVNSPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
Bình Minh Town, Vĩnh Long

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan Investment and renovation of 87B relay system at 110kV substations in 2022". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan Investment and renovation of 87B relay system at 110kV substations in 2022" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second