Bidder Selection Plan

Project contractor selection plan: Construction of technical infrastructure for the land use right auction area west of Dan Di street, Uy No commune, Dong Anh district

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 18:14 07/07/2023
Contractor Selection Plan ID
PL2200081118-01
Publishing time
16:40 07/07/2023
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Construction of technical infrastructure for the land use right auction area west of Dan Di street, Uy No commune, Dong Anh district
Name of project
Construction of technical infrastructure for the land use right auction area west of Dan Di street, Uy No commune, Dong Anh district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Location
Authority that issues the decision
UBND huyện Đông Anh
Approval date
07/07/2023
Approval ID
5618/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 12
1.Tender package No 01: Construction and installation
Tender/ Prequalification Notice ID
Contract execution period
500 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Location
Đông Anh District, Hà Nội
2.Package 02: Power supply
Tender/ Prequalification Notice ID
Contract execution period
500 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
3.Tender package No 08: Audit
Tender/ Prequalification Notice ID
Contract execution period
650 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
4.Package 12: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
865 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
5.Package 04: Consulting on E-HSMT preparation, E-HSDT evaluation for Packages 01 and 02
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
6.Package 05: E-HSMT appraisal consultancy, contractor selection results for package number 01 and 02
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
7.Package 06: E-HSMT preparation consultancy, E-HSDT evaluation of supervision consultancy bidding package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
8.Package 10: E-HSMT appraisal consultancy, contractor selection results for Audit package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
9.Tender package No 11: Clearing mines
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
10.Package 03: Supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
500 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
11.Package 07: E-HSMT appraisal consultancy, contractor selection results for supervision consultancy bidding package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội
12.Package 09: Consulting on E-HSMT preparation, E-HSDT evaluation for Auditing package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Đông Anh District, Hà Nội

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Construction of technical infrastructure for the land use right auction area west of Dan Di street, Uy No commune, Dong Anh district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Construction of technical infrastructure for the land use right auction area west of Dan Di street, Uy No commune, Dong Anh district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second