Bidder Selection Plan

Project: Construction of 35kV power transmission line circuit in Nam Nhun town area + 35kV transmission line construction in Chan Nua - Tia Tau (phase 2)

  Watching  
Project Contractor selection plan Bid award
Find: 12:36 29/06/2023
Contractor Selection Plan ID
PL2300106521-00
Publishing time
09:06 29/06/2023
Posting Status
Published
Contractor selection plan name
Project: Construction of 35kV power transmission line circuit in Nam Nhun town area + 35kV transmission line construction in Chan Nua - Tia Tau (phase 2)
Investment objective
-Improve the reliability of power supply for customers in the area of ​​Nam Nhun district.-It is convenient to apply automation solutions, multi-split-multiplexing in the next stage, quickly isolate the fault area and supply power back to the loads.-Create regional loops and interconnection loops between the lines between 372E29.3 and 371E29.3, 374E29.6, 373E29.4; Road 371E29.3 with 372E29.3, 375E29.4.-Increasing economic benefits for customers and Lai Chau Power Company, reducing customers' loss of electricity
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300029145-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
9 Month
Location
Authority that issues the decision
Công ty Điện lực Lai Châu - Chi nhánh Tổng Công ty Điện lực Miền Bắc
Approval date
28/06/2023
Approval ID
550/QĐ-PCLC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.Tender package TV01: Survey consultancy, data collection, surveying tasks, preparation of construction technical reports
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
NPC's Science and Technology
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Sìn Hồ District, Lai Châu

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project: Construction of 35kV power transmission line circuit in Nam Nhun town area + 35kV transmission line construction in Chan Nua - Tia Tau (phase 2)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project: Construction of 35kV power transmission line circuit in Nam Nhun town area + 35kV transmission line construction in Chan Nua - Tia Tau (phase 2)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second