Bidder Selection Plan
Plan to select contractor for the project of Model Cultural Village in Dong Bua village, Tam Quan commune, Tam Dao district, Vinh Phuc province
Contractor Selection Plan ID
PL2300054918-00
Publishing time
14:43 19/04/2023
Contractor selection plan name
Plan to select contractor for the project of Model Cultural Village in Dong Bua village, Tam Quan commune, Tam Dao district, Vinh Phuc province
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300015960-00
Spending Category
Investment and Development Spending
Project implementation time
2 Years
Location
Vinh Phuc province
Authority that issues the decision
Ủy ban nhân dân huyện Tam Đảo
Approval ID
Số 565/QĐ-UBND
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
File can only be downloaded on Windows computers using Agent, please see instructions here! ! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 14
1. Design of BVTC - DT (Items of moving power line clearance)
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
2. Construction insurance (Items of moving power line clearance)
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
3. Consultancy and design verification of BVTC - DT (Items of moving power line clearance)
Tender/ Prequalification Notice ID
Contract execution period
5 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
4. Consulting to verify the cost estimate of the bidding package (Items of moving power line clearance)
Tender/ Prequalification Notice ID
Contract execution period
5 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
5. Consultancy and design verification of BVTC - DT
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
6. Consultancy on preparation of bidding documents, evaluation of construction bids
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Tender/ Prequalification Notice ID
Contract execution period
7 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
8. Power line relocation (including backup costs)
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
9. Design consultancy BVTC - DT
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
10. Consulting to verify the cost estimate of the bidding package
Tender/ Prequalification Notice ID
Contract execution period
5 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
11. Construction supervision consultant (Items of moving power line clearance)
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Tender/ Prequalification Notice ID
Contract execution period
7 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
13. Construction supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
7 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
14. Consultancy on verification of bidding documents and results of construction and installation documents
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to select contractor for the project of Model Cultural Village in Dong Bua village, Tam Quan commune, Tam Dao district, Vinh Phuc province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Plan to select contractor for the project of Model Cultural Village in Dong Bua village, Tam Quan commune, Tam Dao district, Vinh Phuc province" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.