Bidder Selection Plan

contractor selection plan Project: Binh Tan 110kV station and connection line, Vinh Long province under the AFD . project

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 15:54 06/07/2023
Contractor Selection Plan ID
PL2300112122-00
Publishing time
15:49 06/07/2023
Posting Status
Published
Contractor selection plan name
contractor selection plan Project: Binh Tan 110kV station and connection line, Vinh Long province under the AFD . project
Investment objective
Binh Tan 110kV station and connection line, Vinh Long province under the AFD . project
Project management forms
The investor directly manages the project
Using ODA capital?
Have
Funding source
ODA capital
Project number
PR2300030660-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
5 Years
Location
Authority that issues the decision
Tổng công ty Điện lực miền Nam
Approval date
28/06/2023
Approval ID
1154/QĐ-EVNSPC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Package 02-BT: Supervision of construction and installation of VTTB
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNSPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 04-BT: Provides 110kV control, 110kV protection cabinets, outdoor wiring cabinets, AC & DC cabinets, RTU cabinets and capacitors
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNSPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
3.Package 06-BT: Calibration test of VTTB of the whole station, TTLL system, SCADA and test of line parameter measurement
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNSPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
4.Package 05-BT: Supply, construction and installation of VTTB of Binh Tan 110kV station and connection lines (including relay adjustment calculation, energizing method, operation and troubleshooting)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
AFD & EVNSPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
Fixed unit price
Prequalification
No
Location
5.Package 03-BT: Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNSPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "contractor selection plan Project: Binh Tan 110kV station and connection line, Vinh Long province under the AFD . project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "contractor selection plan Project: Binh Tan 110kV station and connection line, Vinh Long province under the AFD . project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second