Bidder Selection Plan

Contractor selection plan for hydraulic frame price investment project in East Trang Bach area

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 13:40 09/06/2023
Contractor Selection Plan ID
PL2300091254-00
Publishing time
13:37 09/06/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan for hydraulic frame price investment project in East Trang Bach area
Investment objective
Maintaining mine output, improving working conditions for employees, improving safety and productivity, contributing to increasing production efficiency of Uong Bi Coal Company-TKV according to the plan assigned by TKV.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300025258-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
Công ty than Uông Bí-TKV
Approval date
02/06/2023
Approval ID
Số 3307/QĐ-TUB
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Tender package No 02: Project Management Consulting
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and other lawful capital sources of the Investor
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
Đông Triều District, Quảng Ninh
2.Tender package No 03: Supply of anti-stall equipment
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and other lawful capital sources of the Investor
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
Đông Triều District, Quảng Ninh
3.Tender package No 04: Audit cost
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and other lawful capital sources of the Investor
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Đông Triều District, Quảng Ninh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for hydraulic frame price investment project in East Trang Bach area". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for hydraulic frame price investment project in East Trang Bach area" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second