Bidder Selection Plan

Construction planning for the overall project of Tan Cang 220 kV station - Thu Thiem 110 kV substation connecting branch (Branch connecting 110 kV Thu Thiem station)

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 14:35 27/04/2023
Contractor Selection Plan ID
PL2300011234-01
Publishing time
14:33 27/04/2023
Posting Status
Published
Contractor selection plan name
Construction planning for the overall project of Tan Cang 220 kV station - Thu Thiem 110 kV substation connecting branch (Branch connecting 110 kV Thu Thiem station)
Name of project
220 kV Tan Cang Substation - Branch connecting 110 kV Thu Thiem station (Branch connecting 110 kV Thu Thiem station)
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Location
Ho Chi Minh city
Authority that issues the decision
Tổng công ty Điện lực TP.HCM TNHH
Approval date
27/04/2023
Approval ID
1821/QĐ-EVNHCMC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Tender package No 3: Construction supervision.
Tender/ Prequalification Notice ID
Contract execution period
420 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Construction investment capital of EVNHCMC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 1: Supply and install 110 kV underground cable (01 circuit), accessories from JP 1.8 tunnel to 220 kV Tan Cang station and dig, re-establish cable ditch, build cable support foundation at Saigon 2 bridge and buy construction insurance.
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Construction investment capital of EVNHCMC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
3.Package 4: Testing the line.
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Construction investment capital of EVNHCMC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
4.Package 2: Supply and installation of 110 kV underground cable, accessories from 220 kV Thu Thiem station to 220 kV Tan Cang station (01 circuit) and supply and installation of 110 kV underground cable (01 circuit) from 220 kV Thu station Thiem to the JP 1.6 tunnel.
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Construction investment capital of EVNHCMC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
Fixed unit price
Prequalification
No
Location
5.Package 5: Audit of completion of the work.
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Construction investment capital of EVNHCMC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction planning for the overall project of Tan Cang 220 kV station - Thu Thiem 110 kV substation connecting branch (Branch connecting 110 kV Thu Thiem station)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction planning for the overall project of Tan Cang 220 kV station - Thu Thiem 110 kV substation connecting branch (Branch connecting 110 kV Thu Thiem station)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second