Bidder Selection Plan

Construction of a 3-storey classroom house of An Duong Primary School

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 17:19 23/06/2023
Contractor Selection Plan ID
PL2300102792-00
Publishing time
17:13 23/06/2023
Posting Status
Published
Contractor selection plan name
Construction of a 3-storey classroom house of An Duong Primary School
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300028115-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Location
Authority that issues the decision
Ủy ban nhân dân huyện An Dương
Approval date
14/06/2023
Approval ID
1607/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Package 04: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
2.Package 07: Construction insurance costs
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
3.Tender package No 05: Static compression of bamboo poles
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
4.Tender package No 03: Construction - Construction works
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
5.Tender package No 01: E-HSMT preparation, E-HSDT evaluation for construction part
Tender/ Prequalification Notice ID
Contract execution period
25 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
6.Package 06: Cost of independent audit
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
7.Package 02: E-HSMT appraisal, E-KQLCNT appraisal for construction and installation part
Tender/ Prequalification Notice ID
Contract execution period
25 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Public investment belongs to the district's 5-year medium-term plan 2021 - 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Construction of a 3-storey classroom house of An Duong Primary School". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Construction of a 3-storey classroom house of An Duong Primary School" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second