Bidder Selection Plan

Approving the contractor selection plan in the stage of preparation for investment and construction of the repair work of cluster 6, Tieu Can town (the pair of Long Son pagodas) phase 2

  Watching  
Project Contractor selection plan Bid award
Find: 17:41 07/07/2023
Contractor Selection Plan ID
PL2300113276-00
Publishing time
17:32 07/07/2023
Posting Status
Published
Contractor selection plan name
Approving the contractor selection plan in the stage of preparation for investment and construction of the repair work of cluster 6, Tieu Can town (the pair of Long Son pagodas) phase 2
Investment objective
In order to overcome the damaged road surface, complete the traffic network. Strengthening the essential infrastructure system for production, business and people's livelihood, contributing to promoting socio-economic development and improving people's lives; urban embellishment, increase the beauty.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300030954-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
Phòng Kinh tế và Hạ tầng huyện Tiểu Cần
Approval date
05/11/2022
Approval ID
165/QĐ-PKTHT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
422 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Support to complete class IV . urban areas
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Tiểu Cần District, Trà Vinh
2.Consulting, surveying, preparing economic - technical reports
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Support to complete class IV . urban areas
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Tiểu Cần District, Trà Vinh
3.Consultancy and verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Support to complete class IV . urban areas
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
Tiểu Cần District, Trà Vinh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approving the contractor selection plan in the stage of preparation for investment and construction of the repair work of cluster 6, Tieu Can town (the pair of Long Son pagodas) phase 2". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approving the contractor selection plan in the stage of preparation for investment and construction of the repair work of cluster 6, Tieu Can town (the pair of Long Son pagodas) phase 2" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second