Bidder Selection Plan

adjust the contractor selection plan Project: Thanh Tan 110kV substation and connecting branch

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 15:21 06/07/2023
Contractor Selection Plan ID
PL2300112005-00
Publishing time
15:18 06/07/2023
Posting Status
Published
Contractor selection plan name
adjust the contractor selection plan Project: Thanh Tan 110kV substation and connecting branch
Investment objective
110kV Thanh Tan substation and connecting branch
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300030595-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
5 Years
Location
Authority that issues the decision
Tổng công ty Điện lực miền Nam
Approval date
23/06/2023
Approval ID
1096/QĐ-EVNSPC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Package 08-TT: Supply, construction and installation of VTTB of Thanh Tan 110kV substation and connection lines (excluding power transformers, self-contained transformers, 110kV first equipment (outdoor), 24kV assembly cabinets , 110kV control cabinet, 110kV protection cabinet, AC&DC cabinet, charging cabinet)
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans commerce and own capital by SPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
Fixed unit price
Prequalification
No
Location
2.Package 10-TT: Relay setting calculation, setting up method of energizing, operating and troubleshooting the extension compartment (if any)
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and equity of SPC
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
3.Package 06-TT: Provide power transformer, used transformer and attached VTTB
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and equity of SPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
4.Package 07-TT: Supplying the first equipment 110kV (outdoor), 24kV assembly cabinets, 110kV control cabinets, 110kV protection cabinets, AC & DC cabinets, charging cabinets (Not including capacitors, medium voltage transformers, cabinets, etc.) outdoor wiring, battery pack)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and equity of SPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
5.Package 04-TT: Supervision of construction and installation of VTTB
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans commerce and own capital by SPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
6.Package 09-TT: Experiment to calibrate VTTB of the whole station, TTLL system, SCADA, experiment to measure line parameters
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loans and equity of SPC
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
7.Package 05-TT: Audit consulting
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans commerce and own capital by SPC
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "adjust the contractor selection plan Project: Thanh Tan 110kV substation and connecting branch". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "adjust the contractor selection plan Project: Thanh Tan 110kV substation and connecting branch" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second