Status
Tender opening completed
Bidding package name
Package 06 (Construction): Alley 5, inter-hamlet 1-3, Phuoc Binh commune
Investor
CÔNG TY TNHH ĐẦU TƯ VÀ XÂY DỰNG TRƯỜNG THÀNH PHÁT
Bidding Procedure
One stage one bag of records
Contractor Selection Plan ID
Contractor Selection Plan Name
Contract execution period
60 day
Contractor selection methods
Competitive offer
Award date
08:00 28/04/2023
Bid opening completion time
08:00 28/04/2023
Total Number of Bidders
1
Technical Evaluation
Mark