Status
Completing bid evaluation
Bidding package name
Package 03: Consulting survey, design BVTC - construction cost estimate
Investor
Ban Quản lý dự án đầu tư xây dựng huyện Phú Xuyên
Bidding Procedure
One stage two dossier bags
Contractor Selection Plan ID
Contractor Selection Plan Name
Contract execution period
90 day
Contractor selection methods
Open bidding
Award date
16:00 20/04/2023
Bid opening completion time
16:14 20/04/2023
Total Number of Bidders
1
Technical Evaluation
Mark