Status
Tender opening completed
Bidding package name
Package 02: Procurement and installation of equipment
Investor
Học viện Biên phòng
Bidding Procedure
One stage one bag of records
Contractor Selection Plan ID
Contractor Selection Plan Name
Approval of the Estimate, technical specifications and contractor selection plan under the Plan: Procurement and installation of 24000 BTU air conditioners
Contract execution period
10 day
Contractor selection methods
Competitive offer
Award date
08:15 27/04/2023
Bid opening completion time
11:48 27/04/2023
Total Number of Bidders
4