Verification of the F/S/E&S for the Construction Investment, the Expense and the Project Calculating 02 projects "Installing 2 110kV substations at Long Thanh airport (40MVA)" and "Elevating the high phase - ground at about pole 03-04 110kV line 2 circuits 177 Long Binh - 171 Amata 2; 176 Long Binh – 171 An Binh”

Watching    
Project Overall procurement plan Contractor selection plan
Found: 12:15 12/05/2023
Project number
PR2300019876-00
Notice type
Real announcement
Project name
Verification of the F/S/E&S for the Construction Investment, the Expense and the Project Calculating 02 projects "Installing 2 110kV substations at Long Thanh airport (40MVA)" and "Elevating the high phase - ground at about pole 03-04 110kV line 2 circuits 177 Long Binh - 171 Amata 2; 176 Long Binh – 171 An Binh”
Project objective
Verification of the F/S/E&S for the Construction Investment, the Expense and the Project maths
Investor ID
vnz000013106
Authority
Mr: Nguyen Ngoc Thanh - Director of Dong Nai Electricity One Member Co., Ltd
Project duration
2 Year
Project Category
Group C
Project management Type
The investor directly manages the project
Use of ODA funds
No
Implementation location
Dong Nai province
Investment Total Value
To view full information please Login or Register VNĐ
Amount in text format
Project approval ID
702/QĐ-PCĐN
Project approval date
13/04/2023
Approval authority
Công ty TNHH MTV Điện lực Đồng Nai
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.To download, please Login or Register

T04-2022 QD PD DTCP tham tra 02 CT.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Contractor selection plans Link
The project does not have any NTFP yet