New construction of 03 22kV feeders from Chuong My 110kV substation to column 39, Highway 470E1.51 after Phu Nghia 110kV substation, Chuc Son 7 substation, Substation Wastewater treatment plant in Ngoc Son CCN
Watching
Project
Overall procurement plan
Contractor selection plan
Project number
PR2300020712-00
Notice type
Real announcement
Project name
New construction of 03 22kV feeders from Chuong My 110kV substation to column 39, Highway 470E1.51 after Phu Nghia 110kV substation, Chuc Son 7 substation, Substation Wastewater treatment plant in Ngoc Son CCN
Project duration
20 Month
Project management Type
The investor hires a project management consultant
Implementation location
Huyện Chương Mỹ, Ha Noi city
Project approval ID
1022/QĐ-PCCHUONGMY
Project approval date
09/05/2023
Approval authority
Công ty Điện lực Chương Mỹ
Approval documents
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.To download, please Login or Register
File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Contractor selection plans Link
The project does not have any NTFP yet