Investment in equipment for production in 2021 Cao Ngan Thermal Power Plant

Watching    
Project Overall procurement plan Contractor selection plan
Found: 10:28 06/06/2023
Project number
PR2300024423-00
Notice type
Real announcement
Project name
Investment in equipment for production in 2021 Cao Ngan Thermal Power Plant
Project objective
replace equipment and machinery in the power production line that are damaged, no longer able to work, and lack capacity. Ensure that all equipment in the power production line operates synchronously and at the right capacity, eliminating equipment problems in production.
Investor ID
vnz000013661
Authority
Chairman of the board
Project duration
2 Year
Project Category
Group C
Project management Type
The investor directly manages the project
Use of ODA funds
No
Implementation location
Thành phố Thái Nguyên, Thai Nguyen province
Investment Total Value
To view full information please Login or Register VNĐ
Amount in text format
Project approval ID
1508/QĐ-ĐLTKV
Project approval date
24/08/2021
Approval authority
Tổng công ty Điện lực - TKV
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.To download, please Login or Register

1508 QD DA thietbi nam 2021.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Contractor selection plans Link
The project does not have any NTFP yet
You did not use the site, Click here to remain logged. Timeout: 60 second